To include the clashes in task management, you create a separate task for each clash detected. Depending on the editing status, each clash task goes from “open” to “solved” to “closed”.

To create a task for a clash

This is only possible if ...

→  The Bimplus project is loaded in BIM Explorer (see “Loading the building model into BIM Explorer”)
→  The Clash manager palette is open
→  Clashes have been detected
→  You have the required rights (see “Rights in Bimplus”)

  1. Create a task for each clash detected (red). To do this, click Show table to the right of the Clashes detected for the object class in question.

    The Clashes table appears.

  2. Go to the table and click within any column of the clash for which you want to create a task.

    The Clash properties palette opens on the right side.

  3. Click New task.

    Instead of the Clash properties palette, the Details palette appears.

  4. Complete the information about this clash task (see “Using the Bimplus portal to create, retrieve, and edit tasks”).

  5. Click Save.

    The Responsible person and the people behind Email CC addresses get emails informing them of the new clash task; the clash disappears from the Clashes table.

  6. Show the Clash tasks table. To do this, click Show table to the right of the Open clash tasks for the object class in question.

    The Clash tasks table contains the new clash task. When you look at the Status column, you can see that this clash task is Open.