To include the clashes in task management, you need to create a separate task for each clash detected. Depending on the edit status, each clash task goes from ‘open’ to ‘solved’ to ‘closed’.

To create a task for a clash

Info
iconfalse
titleThis is only possible only if ...

→ You have loaded the → The Bimplus project into is loaded in BIM Viewer Explorer (see "Bauwerksmodell in den BIM Explorer laden")
→ You have the required rights (see "Rights in Bimplus")
→ The Clash manager palette is open
→ You have calculated clashes

  1. Create a task for each clash detected (red). To do this,

  2. go to
  3. click Image Added Show table of clashes in the Clashes line of the relevant object class

  4. and click Image Removed Show table of clashes
  5. .

    The Clashes table opens at the top.

  6. Click within any column of the clash for which you want to create a task.

    The Clash properties palette opens on the right.

  7. Click New task.

    The Clash properties palette closes

  8. and
  9. ; the Details palette opens.

  10. Enter details for this clash task (see "Creating, retrieving and editing tasks using the Bimplus portal").

  11. Click Save.

    The Responsible person and the persons behind Email CC addresses get emails, informing them of the new clash task. At the same time, the program removes this clash from the Clashes table.

  12. Display the Clash tasks table. To do this,

  13. go to
  14. click Image Added Show table of clash tasks in the Open clash tasks line of the relevant object class

  15. and click Image Removed Show table of clash tasks
  16. .

    The Clash tasks table includes the new clash task you just created. When you look at the Status column, you can see that this clash task is set to Open.