When you add your own planning data to a construction project by uploading the data to Bimplus for the first time, you usually create your own specialist model in the Bimplus project. You maintain this model over the course of the construction project.
Click Upload and administrate models.
You can see the specialist models of the current project.
Click Add model.
Select the required IFC file or SketchUp file in the Open dialog box.
Click Open.
You can see the Add model dialog box. Enter a name for the specialist model in the Model name box.
This is the name by which you can identify the planning data after import to Bimplus.
Click Upload.
This uploads the planning data to Bimplus.
As soon as the upload is complete, close the Add model dialog box by clicking CLOSE.
To keep the planning data of your specialist model up to date over the course of the construction project, you must update the planning data saved on Bimplus at regular intervals.
Each time you do this, you can decide to synchronize the current data with the new data or to overwrite it completely. Further on you decide, whether a new revision is created or not.
In the dialog box Update Model you get the following options:
This option uploads only those objects, which have been changed or added new to the model data. Deleted objects will be removed from the model. The model revision remains the same.
This way is faster than the Replace model data option.
This option uploads only those objects, which have been changed or added new to the model data. Deleted objects will be removed from the model. Along with that a new model revision is created.
This way is faster than the Replace model data option.
This option uploads the new model data completely. All model data of the latest revision will be deleted. Issues, spots, comments etc. will remain untouched. The model revision remains the same.
This option uploads the new model data completely. All model data of the latest revision will be deleted. Issues, spots, comments etc. will remain untouched. Along with that a new model revision is created.
Click Upload and administrate models.
You can see the specialist models of the current project.
Open the tree structure on the side menu. Go to the
Model that you want to update, click Options and then Update/New revision.Or:
If
Point to the model that you want to update, click Options and then Update/New revision.
Or:
If
Go to the Options column of the model that you want to update and click Update/New revision.
Select the required IFC file or SketchUp file in the Open dialog box.
Click Open.
You can see the Update model dialog box. Decide whether you want to overwrite the existing model or to synchronize it with the new model data and furtheron a new revision shall be created (see above).
Click UPLOAD.
This uploads the updated planning data to Bimplus.