To include the clashes in task management, you need to create a separate task for each clash detected. Depending on the edit status, each clash task goes from “open” to “solved” to “closed”.

To create a task for a clash

This is only possible if ...

→  The Bimplus project is loaded in BIM Explorer (see “Loading the building model into BIM Explorer”)
→  The Clash manager palette is open
→  There are clashes
→  You have the required rights (see “Rights in Bimplus”)

  1. Create a task for each clash detected (red). To do this, go to the Clashes area of the required object class and click Show table of clashes.

    You can see the Clashes table above the full view.

  2. Click within any column of the clash for which you want to create a task.

    The Clash properties palette opens on the right side.

  3. Click New task.

    The Clash properties palette closes; the Details palette opens.

  4. Enter details for this clash task (compare “Using the Bimplus portal to create, retrieve and edit tasks”).

  5. Click Save.

    The Responsible person and the people behind Email CC addresses get emails informing them of the new clash task. At the same time, the program removes this clash from the Clashes table.

  6. Show the Clash tasks table. To do this, go to the Open clash tasks area of the required object class and click Show table of clash tasks.

    The Clash tasks table includes the new clash task you just created. When you look at the Status column, you can see that this clash task is Open.