Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Content imported from a Scroll Translations translation file.

...

Sv translation
languageen

Anchor
TopseitenanfangTop
seitenanfang

Using In Allplan, you can communicate directly with Bimplus and thus with your planning partners. You do not need the web browser. Just open the Task Board palette in Allplan. You can then retrieve the tasks of a Bimplus project from the Bimplus web platform. In addition, you can create new tasks or edit existing tasks.

Info

Important!
This is only possible if the Allplan project is linked with the Bimplus project. In other words, the Allplan project data have has been uploaded to Bimplus at least once. If this is not so, start by linking the Allplan project with the Bimplus project (see "Linking an Allplan project with a Bimplus project").



Info
iconfalse
titleTopics on this page:

Table of Contents
maxLevel1
indent11px
stylesquare




Displaying

Showing the Task Board palette
Anchor

TaskBoard einblenden (Allplan)
TaskBoard einblenden

Displaying the Task Board

(Allplan)

Displaying

By default, the Task Board

(Allplan)To display

palette is integrated in the palette window in Allplan. You can select it there directly.

If this is not so, you must show the palette first.

To show the Task Board palette in Allplan

Info
iconfalse
titleThis is only possible if ...

→ Allplan →  Allplan is running

  1. Right-click in the workspace and select Task Board on the shortcut menu.

  2. If you have not yet logged signed in to Bimplus from your Allplan workstation:
    Use the BIMPLUS dialog box to log sign in to Bimplus (see “Using Allplan to log sign in to Bimplus).


↑ Back to top



Retrieving tasks from Bimplus

To use Allplan to retrieve tasks created for a Bimplus project

Info
iconfalse
titleThis is only possible if ...

→ You have used →  You signed in to Bimplus via your Allplan workstation to log in to Bimplus (see "Using Allplan to log sign in to Bimplus")
→  The relevant Allplan project is open and linked with a Bimplus project (see "Linking an Allplan project with a Bimplus project")
→ You →  You are a member of the Bimplus project

  1. Select the Tasks über Allplan anlegen, abrufen und bearbeiten (see "Displaying Task Board palette (see “Showing the Task Board palette").

    The Tasks area includes the list of tasks created for the linked Bimplus project. This list updates adapts automatically to reflect the current status on Bimplus.

  2. Click within the right column of the task whose details you want to retrieve. As an alternative, you can also double-click the task.

    The Details palette opens, displaying detailed information about this task. The details you can see are the same as those in the Details palette on the Bimplus portal.


↑ Back to top



Retrieving spots

To use Allplan to retrieve the spots placed for a task

Info
iconfalse
titleThis is only possible if ...

→ You have used →  You signed in to Bimplus via your Allplan workstation to log in to Bimplus (see "Using Allplan to log sign in to Bimplus")
→  The relevant Allplan project is open and linked with a Bimplus project (see "Linking an Allplan project with a Bimplus project")
→ You →  You are a member of the Bimplus project

  1. Select the Tasks über Allplan anlegen, abrufen und bearbeiten (see "Displaying Task Board palette (see “Showing the Task Board palette").

    The Tasks area includes the list of tasks created for the linked Bimplus project. This list updates adapts automatically to reflect the current status on Bimplus.

  2. Click within the right column of the task whose spots you want to retrieve. As an alternative, you can also double-click the task.

    The Details palette opens.

  3. Click Click Spots in the Details palette.

    You can see the list of spots placed for the task in the model on the Bimplus web portal.

  4. Click an entry in the list to set the focus on this spot in the view of the model displayed in the current active viewport.


↑ Back to top



Creating tasks

To use Allplan to create a new task for a Bimplus project

Info
iconfalse
titleThis is only possible if ...

→ You have used →  You signed in to Bimplus via your Allplan workstation to log in to Bimplus (see "Using Allplan to log sign in to Bimplus")
→  The relevant Allplan project is open and linked with a Bimplus project (see "Linking an Allplan project with a Bimplus project")
→  You have the required rights (see "Rights Rechte in Bimplus")

  1. Set Select an appropriate view of the building model in the current active viewport. This view will be saved together with the task.

  2. Select the Tasks über Allplan anlegen, abrufen und bearbeiten (see "Displaying Task Board palette (see “Showing the Task Board palette").

  3. Click New task in the Tasks area.

    The Details palette opens.

  4. Click Image Removed Click Image Added Task details in the Details palette and enter detailed information about this task.

  5. To add comments, attachments or hyperlinks, click Comments, Attachments or Hyperlinks respectively in the Details palette (see “Adding extra further information to tasks).

  6. To set the focus on particular elements or objects, display them in color (see "Marking design elements").

  7. Click Save.

    The program This creates the task, saving the view set (see step 1) together with the task. The Responsible person and the persons people behind Email CC addresses in the Image Added Task details get emails , informing them of the new task.


↑ Back to top



Editing tasks

To use Allplan to edit details of a task

Info
iconfalse
titleThis is only possible if ...

→ You have used →  You signed in to Bimplus via your Allplan workstation to log in to Bimplus (see "Using Allplan to log sign in to Bimplus")
→  The relevant Allplan project is open and linked with a Bimplus project (see "Linking an Allplan project with a Bimplus project")
→  You have the required rights (see "Rights Rechte in Bimplus")

  1. Select the Tasks über Allplan anlegen, abrufen und bearbeiten (see "Displaying Task Board palette (see “Showing the Task Board palette").

    The Tasks area includes the list of tasks created for the linked Bimplus project. This list updates adapts automatically to reflect the current status on Bimplus.

  2. Click within the right column of the task you want to edit. As an alternative, you can also double-click the task.

    The Details palette opens, displaying detailed information about this task. The details you can see are the same as those in the Details palette on the Bimplus portal.

  3. Click Image Removed Click Image Added Task details in the Details palette and change the details of this task details.

  4. To add or change a comment, attachment or hyperlinkchange or add comments, attachments or hyperlinks, click Comments, Attachments or Hyperlinks respectively in the Details palette (see “Adding extra further information to tasks).

  5. If you want, you You can change the view saved for the task (see "Saving a view for a task").

  6. Click Save.

    The Responsible person and the persons people behind Email CC addresses in the Image Added Task details get emails , informing them of the changes in the task.


↑ Back to top



Adding

extra

further information to tasks
Anchor

Adding comments, attachment or hyperlinks to tasks

Kommentare usw. Task anhängen (Allplan)

Adding comments, attachment or hyperlinks to tasks

Kommentare usw. Task anhängen (Allplan)

To use Allplan to add a comment, attachment or hyperlink to a task

Info
iconfalse
titleThis is only possible if ...

→ You have used →  You signed in to Bimplus via your Allplan workstation to log in to Bimplus (see "Using Allplan to log sign in to Bimplus")
→  The relevant Allplan project is open and linked with a Bimplus project (see "Linking an Allplan project with a Bimplus project")
→  You have the required rights (see "Rights Rechte in Bimplus")

  1. Select the Tasks über Allplan anlegen, abrufen und bearbeiten (see "Displaying Task Board palette (see “Showing the Task Board palette").

    The Tasks area includes the list of tasks created for the linked Bimplus project. This list updates adapts automatically to reflect the current status on Bimplus.

  2. Click within the right column of the task you want to edit. As an alternative, you can also double-click the task.

    The Details palette opens.

  3. If you want to add a comment:
    Click Image Removed Comments, type a , go to the Details palette, click Image Added Comments, enter the comment in the text box and click Add comment.

    Or:

    If you want to add an attachment:
    Click , go to the Details palette, click Attachments and then click Add attachment. In Select the file in the Open file dialog box , select the file you want to add and click Open.

    Or:

    If you want to add a hyperlink:
    Click , go to the Details palette, click Hyperlinks, type enter the name and URL of the link and click Save Add hyperlink.

  4. Click Save.

    The Responsible person and the persons people behind Email CC addresses in the Image Added Task details get emails , informing them of the changes in the task.


↑ Back to top



Marking design elements
Anchor

Marking design elements

Konstruktionselemente markieren (Allplan)

Marking design elements

Konstruktionselemente markieren (Allplan)

To use Allplan to mark design elements

Info
iconfalse
titleThis is only possible if ...

→ You have used →  You signed in to Bimplus via your Allplan workstation to log in to Bimplus (see "Using Allplan to log sign in to Bimplus")
→  The relevant Allplan project is open and linked with a Bimplus project (see "Linking an Allplan project with a Bimplus project")
→  You have the required rights (see "Rights Rechte in Bimplus")

  1. Select the Tasks über Allplan anlegen, abrufen und bearbeiten (see "Displaying Task Board palette (see “Showing the Task Board palette").

    The Tasks area includes the list of tasks created for the linked Bimplus project. This list updates adapts automatically to reflect the current status on Bimplus.

  2. Click within the right column of the task for which you want to mark design elements in the model. As an alternative, you can also double-click the task.

    The Details palette opens.

  3. Click Click Select Elements, Clear Selection at the bottom of the Details palette.

  4. In Go to the current active viewport , and click the elements you want to display in color.

  5. Right-click to confirm your settings.

    The Responsible person and the persons people behind Email CC addresses in the Image Added Task details get emails , informing them of the changes in the task.


↑ Back to top



Saving a view for a task
Anchor

Saving a view for a task

Perspektive zu einem Task speichern (Allplan)

Saving a view for a task

Perspektive zu einem Task speichern (Allplan)

Whenever you save changes in the task details, the program saves the view set in the current active viewport together with the task. But you can also change the view saved for a task.

To use Allplan to save a new view for a task

Info
iconfalse
titleThis is only possible if ...

→ You have used →  You signed in to Bimplus via your Allplan workstation to log in to Bimplus (see "Using Allplan to log sign in to Bimplus")
→  The relevant Allplan project is open and linked with a Bimplus project (see "Linking an Allplan project with a Bimplus project")
→  You have the required rights (see "Rights Rechte in Bimplus")

  1. Select the Tasks über Allplan anlegen, abrufen und bearbeiten (see "Displaying Task Board palette (see “Showing the Task Board palette").

    The Tasks area includes the list of tasks created for the linked Bimplus project. This list updates adapts automatically to reflect the current status on Bimplus.

  2. Click within the right column of the task for which you want to save a new view. As an alternative, you can also double-click the task.

    The Details palette opens.

  3. Change the view in the current active viewport.

  4. Click Click Save view. at the bottom of the Details palette.

    The Responsible person and the persons people behind Email CC addresses in the Image Added Task details get emails , informing them of the changes in the task.


↑ Back to top



Importing and exporting tasks

To communicate with your planning partners, you can directly import any task in BCF format (BIM collaboration format) or export any Bimplus task in BCF format.

Info

Important!
The project must include the associated model with the objects described in the task. Otherwise, the program can neither use nor display BCF files correctly. Therefore, load the model into your project before you import BCF files.

To use Allplan to import a task in BCF format

Info
iconfalse
titleThis is only possible if ...

→ You have used →  You signed in to Bimplus via your Allplan workstation to log in to Bimplus (see "Using Allplan to log sign in to Bimplus")
→  The relevant Allplan project is open and linked with a Bimplus project (see "Linking an Allplan project with a Bimplus project")
→  You have the required rights (see "Rights Rechte in Bimplus")

  1. Select the Tasks über Allplan anlegen, abrufen und bearbeiten (see "Displaying Task Board palette (see “Showing the Task Board palette").

  2. Click Import BCF file to Bimplus in the Tasks area.

  3. The Open file dialog box opens. Select the BCF file including the task you want to import. The extension of this file is usually *.BCFZIP.

  4. Click Open.

    This creates a new task, writing the contents of the BCF file to this task.


↑ Back to top

To use Allplan to export a task in BCF format

Info
iconfalse
titleThis is only possible if ...
→ You have used →  You signed in to Bimplus via your Allplan workstation to log in to Bimplus (see "Using Allplan to log sign in to Bimplus")
→  The relevant Allplan project is open and linked with a Bimplus project (see "Linking an Allplan project with a Bimplus project")
→  You have the required rights (see "Rights Rechte in Bimplus")
  1. Select the Tasks über Allplan anlegen, abrufen und bearbeiten (see "Displaying Task Board palette (see “Showing the Task Board palette").

    The Tasks area includes the list of tasks created for the linked Bimplus project. This list updates adapts automatically to reflect the current status on Bimplus.

  2. Select the task you want to export to a BCF file.

    To do this, click within any column of this task in the task list.

  3. Click Export task to BCF file in the Tasks area.

    The BCF createdexport dialog box opens.

  4. Select the BCF format (BCF 2.0 or BCF 2.1).

  5. Decide whether you want to download the file immediately or make it available for other planning partners so that they can download it.

    Download
    Click DOWNLOAD and save the file in

    You can choose to save the file locally on your computer or to send the file immediately to the relevant persons.

    Select Download or Share file respectively.
    If you select the Download option:
    Click the Download button and save the file to

    any folder.

    Or:

    If you select the

    Share file

    option:


    Enter the email addresses of the


    Click within the Email box, select one or more

    recipients and click

    Send

    SEND. The recipients get emails

    ,

    informing them of the BCF file that is available for download on Bimplus.


↑ Back to top



Exporting the task list

It is often difficult to keep track of tasks, in particular, with complex task lists. Therefore, you can export the complete task list of a Bimplus project in Excel format.

To use Allplan to export the task list of a Bimplus project in Excel format

Info
iconfalse
titleThis is only possible if ...
→ You have used →  You signed in to Bimplus via your Allplan workstation to log in to Bimplus (see "Using Allplan to log sign in to Bimplus")
→  The relevant Allplan project is open and linked with a Bimplus project (see "Linking an Allplan project with a Bimplus project")
→  You have the required rights (see "Rights Rechte in Bimplus")
  1. Select the Tasks über Allplan anlegen, abrufen und bearbeiten (see "Displaying Task Board palette (see “Showing the Task Board palette").

    The Tasks area includes the list of tasks created for the linked Bimplus project. This list updates adapts automatically to reflect the current status on Bimplus.

  2. Arrange the columns of the task list in the sequence in which you want to display the columns in Excel.

  3. Sort the rows of the task list in the sequence in which you want to display the rows in Excel.

    To do this, click the column header of which the column you want to use to sort the contents for sorting of the task list alphabetically or numerically in ascending or descending order.

  4. Click Click Export all tasks to Excel file in the Tasks area.

  5. Save the file in any folder or open the file in Excel.

↑ Back to top



Deleting tasks

To use Allplan to delete a task from a Bimplus project

Info
iconfalse
titleThis is only possible if ...

→ You have used →  You signed in to Bimplus via your Allplan workstation to log in to Bimplus (see "Using Allplan to log sign in to Bimplus")
→  The relevant Allplan project is open and linked with a Bimplus project (see "Linking an Allplan project with a Bimplus project")
→  You have the required rights (see "Rights Rechte in Bimplus")

  1. Select the Tasks über Allplan anlegen, abrufen und bearbeiten (see "Displaying Task Board palette (see “Showing the Task Board palette").

    The Tasks area includes the list of tasks created for the linked Bimplus project. This list updates adapts automatically to reflect the current status on Bimplus.

  2. Click within the right column of the task you want to delete. As an alternative, you can also double-click the task.

    The Details palette opens.

  3. Click Click Delete task in the Details palette.

  4. Click

    Yes

    YES to confirm the prompt.

    Warning
    titleATTENTION!

    This deletes the task including all spots and further information not only from Allplan but also from the database saved on the Bimplus web platform for good.



↑ Back to top